Ho75SB

Ho75SB is a 75.0 MW solar + storage request withdrawn in the West interconnection queue, in Otero County, New Mexico, connecting to El Paso Electric Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2025 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q25-LG-6-10-1
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Holloman-Largo 115 kV line
Location
Otero County, New Mexico
Technology
Solar: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
10 June 2025
Proposed online date
September 2028

Location

Marker shows the centre of Otero County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Otero County