🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Mexico

SOLAR + STORAGE · WEST

Solar + storage project GI-DISIS-2021-04, Otero County

Solar + storage project GI-DISIS-2021-04, Otero County is a 150 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Otero County, New Mexico, connecting to Tri-State Generation and Transmission Association.

Queue statusConsented
  1. PlanningQueued May 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-DISIS-2021-04
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Dillard Draw 115kV Switching Station
Location
Otero County, New Mexico
Technology
Solar: 100 MW · Battery: 50.0 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Executed LGIA
Queue status
Active
Entered queue
26 May 2021
Proposed online date
March 2028

Location

Marker shows the centre of Otero County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Otero County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem