SOLAR · WEST

Solar project SGI-PNM-2010-09, Otero County

Solar project SGI-PNM-2010-09, Otero County is a 5.0 MW solar request built and operating in the West interconnection queue, in Otero County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued May 2010 (completed)
  2. ConsentedSep 2018 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2010-09
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM-RGD Alamogordo South Feeder 12-83
Location
Otero County, New Mexico
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
1st Revised SGIA executed 09/25/2018. 2nd Revised SGIA executed 6/5/24.
Queue status
Operational
Entered queue
4 May 2010
Agreement signed
25 September 2018

Location

Marker shows the centre of Otero County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Otero County