HO100SB Project

HO100SB Project is a 100 MW solar + storage request withdrawn in the West interconnection queue, in Otero County, New Mexico, connecting to El Paso Electric Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
LG-19-9-30
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
Holloman substation
Location
Otero County, New Mexico
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
30 September 2019
Proposed online date
December 2022

Location

Marker shows the centre of Otero County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Otero County