United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2021-052, Muskogee County
Battery storage project GEN-2021-052, Muskogee County is a 75.0 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Muskogee County, Oklahoma, connecting to OGE.
Queue statusConsented
- PlanningQueued Apr 2021 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2031 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2021-052
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Pecan Creek 345kV substation
- Location
- Muskogee County, Oklahoma
- Technology
- Battery: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 29 April 2021
- Proposed online date
- June 2031
Location
Marker shows the centre of Muskogee County; the queue data does not give exact sites.
Other requests in Muskogee County
- Solar project GEN-2021-053, Muskogee CountySolar · 300 MW · agreement signed
- Solar project GEN-2017-092, Muskogee CountySolar · 200 MW · agreement signed
- Battery storage project GEN-2018-024, Muskogee CountyBattery storage · 100 MW · agreement signed
- Other project GEN-2025-SR9, Muskogee CountyOther · 410 MW · in study
- Solar project GEN-2024-268, Muskogee CountySolar · 390 MW · in study
- Battery storage project GEN-2025-SR7, Muskogee CountyBattery storage · 102 MW · in study
- Gas project GEN-2000-011, Muskogee CountyGas · 825 MW · withdrawn
- Solar project GEN-2022-224, Muskogee CountySolar · 325 MW · withdrawn
- Onshore wind project GEN-2017-155, Muskogee CountyOnshore wind · 300 MW · withdrawn
- Battery storage project GEN-2022-226, Muskogee CountyBattery storage · 200 MW · withdrawn
- Solar + storage project GEN-2023-131, Muskogee CountySolar + storage · 200 MW · withdrawn
- Battery storage project GEN-2022-225, Muskogee CountyBattery storage · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem