United States › Grid › Interconnection queues › Oklahoma
OTHER · SPPOther project GEN-2025-SR9, Muskogee County
Other project GEN-2025-SR9, Muskogee County is a 410 MW other request in interconnection study in the SPP interconnection queue, in Muskogee County, Oklahoma, connecting to OG&E.
Queue statusIn planning
- PlanningQueued May 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2025-SR9
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OG&E
- Connection point (POI)
- Muskogee 345 KV Substation
- Location
- Muskogee County, Oklahoma
- Technology
- Other: 410 MW
- Total requested
- 410 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 31 May 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Muskogee County; the queue data does not give exact sites.
Other requests in Muskogee County
- Solar project GEN-2021-053, Muskogee CountySolar · 300 MW · agreement signed
- Solar project GEN-2017-092, Muskogee CountySolar · 200 MW · agreement signed
- Battery storage project GEN-2018-024, Muskogee CountyBattery storage · 100 MW · agreement signed
- Battery storage project GEN-2021-052, Muskogee CountyBattery storage · 75.0 MW · agreement signed
- Solar project GEN-2024-268, Muskogee CountySolar · 390 MW · in study
- Battery storage project GEN-2025-SR7, Muskogee CountyBattery storage · 102 MW · in study
- Gas project GEN-2000-011, Muskogee CountyGas · 825 MW · withdrawn
- Solar project GEN-2022-224, Muskogee CountySolar · 325 MW · withdrawn
- Onshore wind project GEN-2017-155, Muskogee CountyOnshore wind · 300 MW · withdrawn
- Battery storage project GEN-2022-226, Muskogee CountyBattery storage · 200 MW · withdrawn
- Solar + storage project GEN-2023-131, Muskogee CountySolar + storage · 200 MW · withdrawn
- Battery storage project GEN-2022-225, Muskogee CountyBattery storage · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem