United States › Grid › Interconnection queues › South Carolina
GAS · SOUTHEASTGas project 20230829006, Jasper County
Gas project 20230829006, Jasper County is a 76.0 MW gas request in interconnection study in the Southeast interconnection queue, in Jasper County, South Carolina, connecting to Dominion Energy South Carolina.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 20230829006
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Dominion Energy South Carolina
- Developer
- DESC - Generation
- Connection point (POI)
- Jasper 230 kV Substation
- Location
- Jasper County, South Carolina
- Technology
- Gas: 76.0 MW
- Total requested
- 76.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Proposed online date
- September 2023
Location
Marker shows the centre of Jasper County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Jasper County
- Gas project 20211104001, Jasper CountyGas · 158 MW · in study
- Solar project 44, Jasper CountySolar · 75.0 MW · built
- Gas project 21, Jasper CountyGas · 620 MW · withdrawn
- Gas project 20, Jasper CountyGas · 620 MW · withdrawn
- Gas project 20200728001, Jasper CountyGas · 360 MW · withdrawn
- Solar project 38, Jasper CountySolar · 74.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem