🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 126

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 126 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2020-078, Washington County
Solar
100 MWAgreement signed Washington, NESPP Apr 2020target 2022
Onshore wind project J2031, Tama County
Onshore wind
100 MWIn study Tama, IAMISO Aug 2021target 2026
SPC Bloom BESS
Battery storage · BRP Blue Topaz 2, LLC
100 MWIn study Victoria, TXERCOT Dec 2020target 2027
Solar + storage project J3181, Logan County
Solar + storage
100 MWIn study Logan, ILMISO Sep 2022target 2027
Blue Rock Solar
Solar
100 MWAgreement signed Buckingham, VAPJM Mar 2019target 2026
IEP Blackhawk
Battery storage · IEP Texas Verde II, llc
100 MWIn study Galveston, TXERCOT Apr 2023target 2026
Solar project J1932, Gladwin County
Solar
100 MWIn study Gladwin, MIMISO Aug 2021target 2024
Battery storage project IA-PNM-2022-11, Bernalillo County
Battery storage
100 MWIn study Bernalillo, NMWest Apr 2022target 2024
Union City Storage II
Battery storage
100 MWIn study Fulton, GASoutheast Dec 20192022
Solar + storage project AI1-081, Jay County
Solar + storage
100 MWIn study Jay, INPJM Jul 2022target 2026
Battery storage project AH2-269, Ocean County
Battery storage
100 MWIn study Ocean, NJPJM Mar 2022target 2026
Surplus
Battery storage
100 MWIn study Perry, ILMISO Jun 2025target 2026
Battery storage project G0828, Grant County
Battery storage
100 MWIn study Grant, WAWest Dec 2022target 2026
Alcazar 1
Battery storage · Terra-Gen Development Company, LLC
100 MWIn study Ulster, NYNYISO Aug 2024target 2028
Solar project J1748, Desoto County
Solar
100 MWAgreement signed Desoto, MSMISO Jul 2020target 2025
Battery storage project J3166, Knox County
Battery storage
100 MWIn study Knox, INMISO Sep 2022target 2026
Surplus; J1314
Other
100 MWIn study Polk, WIMISO Sep 2022target 2025
Other project 116, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Solar + storage project J3186, Bolivar County
Solar + storage
100 MWIn study Bolivar, MSMISO Sep 2022target 2027
Onshore wind project J3990, Mclean County
Onshore wind
100 MWIn study Mclean, ILMISO Apr 2025target 2029
Solar project J1904, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Aug 2021target 2028
Battery storage project 25, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Aug 2022target 2027
Solar project J3379, Johnson County
Solar
100 MWIn study Johnson, ILMISO Apr 2024target 2028
Battery storage project AI2-039, Surry County
Battery storage
100 MWIn study Surry, VAPJM Feb 2023target 2026
Solar + storage project J3112, Phillips County
Solar + storage
100 MWIn study Phillips, ARMISO Sep 2022target 2026
Battery storage project 24-245, Washington County
Battery storage
100 MWIn study Washington, ORWest May 2024target 2027
Battery storage project J2450, Tippecanoe County
Battery storage
100 MWIn study Tippecanoe, INMISO Sep 2022target 2026
Solar project Q254, Pinal County
Solar
100 MWAgreement signed Pinal, AZWest Mar 2017target 2022
Solar project J604, Sunflower County
Solar
100 MWAgreement signed Sunflower, MSMISO May 20162022
Battery storage project J2066, Henry County
Battery storage
100 MWIn study Henry, IAMISO Aug 2021target 2022
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Solar project J3035, Desha County
Solar
100 MWIn study Desha, ARMISO Sep 2022target 2026
Solar + storage project J2133, White County
Solar + storage
100 MWIn study White, ARMISO Aug 2021target 2024
Zinnia Storage
Battery storage
100 MWAgreement signed Bernalillo, NMWest Oct 2020target 2023
Battery storage project GEN-2023-061, Jasper County
Battery storage
100 MWIn study Jasper, MOSPP Oct 2023target 2029
Solar project GEN-2020-092, Mayes County
Solar
100 MWIn study Mayes, OKSPP Apr 2020target 2026
Battery storage project S0025, Natrona County
Battery storage
100 MWIn study Natrona, WYWest Feb 2024target 2026
Battery storage project AH2-233, Pulaski County
Battery storage
100 MWIn study Pulaski, INPJM Mar 2022target 2026
Riverstart Solar Park V
Solar
100 MWPaused / redesign Randolph, INPJM Mar 2019target 2026
AN100S
Solar
100 MWAgreement signed Luna, NMWest Mar 2024target 2027
Solar project AG2-114, Livingston County
Solar · CPV Prairie Dock Solar, LLC
100 MWIn study Livingston, ILPJM Feb 2025target 2024
Solar project J1426, Benton County
Solar
100 MWUnder construction Benton, MNMISO Apr 2019target 2025
Onshore wind project J569, Rock County
Onshore wind
100 MWAgreement signed Rock, MNMISO May 20162022
Solar + storage project Q97, Nez Perce County
Solar + storage
100 MWIn study Nez Perce, IDWest
Nicholas Solar
Solar
100 MWAgreement signed Nicholas, WVPJM Mar 2020target 2029
Bakers Pond Solar
Solar
100 MWPaused / redesign Prince George, VAPJM Sep 2018target 2026
Solar + storage project 20230825001, Colleton County
Solar + storage
100 MWIn study Colleton, SCSoutheast target 2026
Battery storage project Company 161, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Mar 2018target 2021
Yadkins Energy Center
Battery storage · Yadkins Energy Center, LLC
100 MWIn study City Of Chesapeake, VAPJM Mar 2019target 2021
Solar project CSUT-2025-2, El Paso County
Solar
100 MWIn study El Paso, COWest Mar 2025target 2028
Page 126 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)