SOLAR + STORAGE · MISO

Solar + storage project J2133, White County

Solar + storage project J2133, White County is a 100 MW solar + storage request in interconnection study in the MISO interconnection queue, in White County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2133
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Garner 115 kV Substation
Location
White County, Arkansas
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
26 August 2021
Proposed online date
April 2024

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in White County