United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J2742, White County
Solar project J2742, White County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in White County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2742
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- BEEBE - GARNER SS 115.0kV
- Location
- White County, Arkansas
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 13 September 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of White County; the queue data does not give exact sites.
Other requests in White County
- Solar + storage project J2133, White CountySolar + storage · 100 MW · in study
- Solar project J893, White CountySolar · 100 MW · built
- Solar project J1373, White CountySolar · 95.0 MW · built
- Solar + storage project J2854, White CountySolar + storage · 150 MW · withdrawn
- Solar project J3531, White CountySolar · 100 MW · withdrawn
- Solar project J1134, White CountySolar · 100 MW · withdrawn
- Solar project J653, White CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem