United States › Grid › Interconnection queues › Arkansas

SOLAR · MISO

Solar project J893, White County

Solar project J893, White County is a 100 MW solar request built and operating in the MISO interconnection queue, in White County, Arkansas, connecting to Entergy.

Queue statusOperating
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedNov 2019 (completed)
  3. Construction (completed)
  4. OperatingAug 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J893
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
Searcy Price Sub 161kV
Location
White County, Arkansas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
16 June 2017
Agreement signed
20 November 2019
Proposed online date
August 2021
Came online
August 2021

Location

Marker shows the centre of White County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in White County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem