United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · MISO

Onshore wind project J2031, Tama County

Onshore wind project J2031, Tama County is a 100 MW onshore wind request in interconnection study in the MISO interconnection queue, in Tama County, Iowa, connecting to ITC MIDWEST.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2031
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Toledo
Location
Tama County, Iowa
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 August 2021
Proposed online date
December 2026

Location

Marker shows the centre of Tama County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Tama County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem