ONSHORE WIND · MISOOnshore wind project H009, Tama County
Onshore wind project H009, Tama County is a 150 MW onshore wind request built and operating in the MISO interconnection queue, in Tama County, Iowa.
Request details
- Queue ID
- H009
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- ITC Midwest Traer - Marshalltown 161 kV
- Location
- Tama County, Iowa
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 22 April 2008
- Agreement signed
- 1 April 2015
- Proposed online date
- December 2010
- Came online
- December 2010
Location
Marker shows the centre of Tama County; the queue data does not give exact sites.
Other requests in Tama County
- Onshore wind project J1365, Tama CountyOnshore wind · 169 MW · in study
- Onshore wind project J2031, Tama CountyOnshore wind · 100 MW · in study
- Other project G286, Tama CountyOther · 4.0 MW · built
- Onshore wind project J298, Tama CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J461, Tama CountyOnshore wind · 299 MW · withdrawn
- Battery storage project J2095, Tama CountyBattery storage · 212 MW · withdrawn
- Solar project J3462, Tama CountySolar · 187 MW · withdrawn
- Onshore wind project J096, Tama CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project J114, Tama CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project H039, Tama CountyOnshore wind · 71.0 MW · withdrawn
- Onshore wind project J3544, Tama CountyOnshore wind · 62.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem