United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project H039, Tama County

Onshore wind project H039, Tama County is a 71.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Tama County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedOct 2008 (project stopped here)
  3. ConsentedOct 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H039
Grid region
MISO (Midcontinent)
Connection point (POI)
Toledo - Marshalltown 115 kV
Location
Tama County, Iowa
Technology
Wind: 71.0 MW
Total requested
71.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
6 June 2008
Agreement signed
9 October 2008
Proposed online date
January 2011
Withdrawn
October 2008

Location

Marker shows the centre of Tama County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Tama County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem