United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project J1365, Tama County
Onshore wind project J1365, Tama County is a 169 MW onshore wind request in interconnection study in the MISO interconnection queue, in Tama County, Iowa, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Apr 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1365
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Traer 161-kV Substation
- Location
- Tama County, Iowa
- Technology
- Wind: 169 MW
- Total requested
- 169 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 29 April 2019
- Proposed online date
- September 2024
Location
Marker shows the centre of Tama County; the queue data does not give exact sites.
Other requests in Tama County
- Onshore wind project J2031, Tama CountyOnshore wind · 100 MW · in study
- Onshore wind project H009, Tama CountyOnshore wind · 150 MW · built
- Other project G286, Tama CountyOther · 4.0 MW · built
- Onshore wind project J298, Tama CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J461, Tama CountyOnshore wind · 299 MW · withdrawn
- Battery storage project J2095, Tama CountyBattery storage · 212 MW · withdrawn
- Solar project J3462, Tama CountySolar · 187 MW · withdrawn
- Onshore wind project J096, Tama CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project J114, Tama CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project H039, Tama CountyOnshore wind · 71.0 MW · withdrawn
- Onshore wind project J3544, Tama CountyOnshore wind · 62.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem