🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

BATTERY STORAGE · SOUTHEAST

Union City Storage II

Union City Storage II is a 100 MW battery storage request in interconnection study in the Southeast interconnection queue, in Fulton County, Georgia, connecting to Georgia Transmission.

Queue statusIn planning
  1. PlanningQueued Dec 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingSep 2022 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-133
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Union City substation
Location
Fulton County, Georgia
Technology
Battery: 100 MW
Total requested
100 MW
Study phase
Facilities Study
Queue status
Active
Entered queue
11 December 2019
Proposed online date
November 2022
Came online
September 2022

Location

Marker shows the centre of Fulton County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Fulton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem