🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

SOLAR · PJM

Solar project AG2-114, Livingston County

Solar project AG2-114, Livingston County is a 100 MW solar request in interconnection study in the PJM interconnection queue, in Livingston County, Illinois, connecting to ComEd.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-114
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
CPV Prairie Dock Solar, LLC
Connection point (POI)
Dresden-Pontiac Midpoint 345 kV
Location
Livingston County, Illinois
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
14 February 2025
Proposed online date
March 2024

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Livingston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem