🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · PJM

Cayuga Ridge South WF

Cayuga Ridge South WF is a 300 MW onshore wind request built and operating in the PJM interconnection queue, in Livingston County, Illinois, connecting to ComEd.

Queue statusOperating
  1. PlanningQueued Jul 2005 (completed)
  2. ConsentedSep 2009 (completed)
  3. Construction (completed)
  4. OperatingDec 2007 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
O51
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Pontiac Midpoint-Wilton Center 345kV
Location
Livingston County, Illinois
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
27 July 2005
Agreement signed
8 September 2009
Proposed online date
May 2010
Came online
December 2007

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Livingston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem