Pleasant Ridge Wind Farm

Pleasant Ridge Wind Farm is a 500 MW onshore wind request withdrawn in the PJM interconnection queue, in Livingston County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandonedAug 2019 (project stopped here)
  3. ConsentedAug 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R30
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Pontiac Mid-Point 345kV
Location
Livingston County, Illinois
Technology
Wind: 500 MW
Total requested
500 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
24 October 2006
Agreement signed
7 August 2014
Proposed online date
December 2020
Withdrawn
August 2019

Location

Marker shows the centre of Livingston County; the queue data does not give exact sites.