United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project J569, Rock County

Onshore wind project J569, Rock County is a 100 MW onshore wind request with a signed interconnection agreement in the MISO interconnection queue, in Rock County, Minnesota.

Queue statusConsented
  1. PlanningQueued May 2016 (completed)
  2. ConsentedFeb 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingDec 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J569
Grid region
MISO (Midcontinent)
Connection point (POI)
NSP Rock County Substation
Location
Rock County, Minnesota
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
GIA
Queue status
Active
Entered queue
6 May 2016
Agreement signed
13 February 2020
Proposed online date
October 2021
Came online
December 2022

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Rock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem