United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA — page 32
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Green Palms Solar |
307 MW | In study |
| Laurel Wind Energy Center Onshore wind · LAUREL ENERGY CENTER, LLC |
307 MW | Agreement signed |
| Copperleaf Energy Storage Battery storage · Copperleaf Energy Storage, LLC |
307 MW | In study |
| Gilleys Energy Storage Battery storage · Gilleys Energy Storage, LLC |
306 MW | In study |
| McCrae Energy Storage Battery storage · McCrae Energy Storage, LLC |
306 MW | Agreement signed |
| O'Bannion Energy Storage Battery storage · O'Bannion Energy Storage, LLC |
306 MW | Agreement signed |
| Wooderson Energy Storage Battery storage · Wooderson Energy Storage, LLC |
306 MW | In study |
| Southfork Energy Storage Battery storage · Southfork Energy Storage, LLC |
306 MW | In study |
| Blue Skies BESS Battery storage · ACTX BESS Project LLC |
306 MW | Agreement signed |
| Wolf Hollow III Gas · Wolf Hollow II Power LLC |
306 MW | In study |
| Spur Energy Storage Battery storage · Spur Energy Storage, LLC |
306 MW | In study |
| Solar project GEN-2021-023, Grant County Solar |
306 MW | Agreement signed |
| Straight Spur Storage Solar + storage · ENGIE IR Holdings LLC |
306 MW | In study |
| Aurora Energy Storage Battery storage · Aurora Energy Storage, LLC |
306 MW | In study |
| Damia Solar Solar + storage · Damia Solar, LLC |
306 MW | In study |
| Winston Hybrid PV And BESS Solar + storage |
306 MW | Agreement signed |
| Estrella Dorada Wind Onshore wind · Estrella Dorada Wind Farm, LLC |
306 MW | In study |
| Lite Brite Battery Storage Battery storage |
306 MW | Agreement signed |
| Velveteen Solar II Solar · Velveteen Solar II, LLC |
306 MW | In study |
| Cuchillas Solar Solar + storage · Gransolar Texas Two, LLC |
306 MW | Agreement signed |
| Serenity Solar |
305 MW | In study |
| Glory Bee Solar Solar + storage · Riley Solar LLC |
305 MW | In study |
| Lake Henry Wind Onshore wind |
305 MW | Paused / redesign |
| Humidor Storage 1 Battery storage |
305 MW | Agreement signed |
| Academy Wind Onshore wind |
305 MW | Paused / redesign |
| Gosford Solar Storage Solar |
305 MW | In study |
| Gnarly Osage Battery storage |
304 MW | In study |
| Panhandle Flagship Solar 2 Solar + storage · Panhandle Solar Group Operating Company LLC |
304 MW | Agreement signed |
| Glass Mountain Solar 2 Solar · Glass Mountain Solar, LLC |
304 MW | In study |
| WOE Gyp King Wind Onshore wind · KSK Wind Farm 1, LLC |
304 MW | Paused / redesign |
| Glass Mountain Solar 1 Solar · Glass Mountain Solar, LLC |
304 MW | In study |
| Glass Mountain Solar Solstice Solar · Glass Mountain Solar, LLC |
304 MW | In study |
| Twinkle Battery storage |
304 MW | In study |
| Furay Battery Energy Storage System Battery storage · Blue Topaz 1, LLC |
304 MW | In study |
| Solar project J4132, Benton County Solar |
304 MW | In study |
| Bullring Wind 2 Onshore wind · Halcon Wind, LLC |
304 MW | Agreement signed |
| NavBoot BESS Battery storage · Navboot BESS LLC |
304 MW | Agreement signed |
| Juanita Creek BESS Battery storage · Juanita Creek Energy Center, LLC |
304 MW | In study |
| BRP Aras BESS Battery storage · BRP Aras BESS LLC |
304 MW | In study |
| Replacing 303.5 MW BESS with 303.5 MW COAL; Edgewater Unit 5 Other |
304 MW | In study |
| Bullring Wind 1 Onshore wind · Halcon Wind, LLC |
304 MW | Agreement signed |
| Wander Waters BESS Battery storage · Wander Waters BESS LLC |
304 MW | In study |
| Goat Mountain Wind-Repower Wind + storage · Goat Wind LLC |
303 MW | In study |
| Gas project GEN-2024-211, Cass County Gas |
303 MW | In study |
| Gas project GEN-2024-212, Cass County Gas |
303 MW | In study |
| Roccasecca BESS Battery storage |
303 MW | Agreement signed |
| Prairie Power Wind Onshore wind · Prairie Power Wind, LLC |
303 MW | In study |
| Old Aqueduct Batt Solar + storage · Old Aqueduct LLC |
303 MW | In study |
| Live Oak Wind II Onshore wind · ENGIE IR Holdings LLC |
303 MW | In study |
| Brantley Branch Batt Battery storage · Brantley Branch LLC |
302 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,857 · 519.1 GW
- ERCOT (Texas)1,986 · 447.3 GW
- MISO (Midcontinent)1,646 · 350.1 GW
- CAISO (California)429 · 188.6 GW
- Southeast (non-ISO utilities)1,067 · 161.4 GW
- SPP (Southwest Power Pool)692 · 152.4 GW
- PJM (Mid-Atlantic, Midwest)1,248 · 140.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)72 · 14.6 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)