United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTAcademy Wind
Academy Wind is a 305 MW onshore wind request suspended in the ERCOT interconnection queue, in Dickens County, Texas.
Queue statusPaused / redesign
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0151
- Grid region
- ERCOT (Texas)
- Location
- Dickens County, Texas
- Technology
- Wind: 305 MW
- Total requested
- 305 MW
- Queue status
- Suspended
- Entered queue
- 14 September 2022
- Proposed online date
- December 2028
Location
Marker shows the centre of Dickens County; the queue data does not give exact sites.
Other requests in Dickens County
- Wolf Spring StorageSolar + storage Β· 203 MW Β· agreement signed
- Donegal SolarSolar Β· 202 MW Β· agreement signed
- Wolf Spring SolarSolar + storage Β· 196 MW Β· agreement signed
- Corruscant BESSBattery storage Β· 402 MW Β· in study
- Spurland Solar ISolar Β· 302 MW Β· in study
- Outrider BESSBattery storage Β· 302 MW Β· in study
- Sanders Hollow Energy CenterOnshore wind Β· 293 MW Β· in study
- Timberlakes SolarSolar Β· 204 MW Β· in study
- Spurland Solar IISolar Β· 202 MW Β· in study
- Dickens BESSOther Β· 201 MW Β· built
- Burksol BESSOther Β· 103 MW Β· built
- Aquamarine SolarSolar Β· 152 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem