SOLAR + STORAGE · ERCOTWolf Spring Storage
Wolf Spring Storage is a 203 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Dickens County, Texas.
Queue statusConsented
- PlanningQueued Dec 2022 (completed)
- ConsentedAug 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 25INR0173
- Grid region
- ERCOT (Texas)
- Developer
- Wolf Spring Solar, LLC
- Connection point (POI)
- Tap 345kV 59904 Cotton Wood - 23922 White River Ckt 1
- Location
- Dickens County, Texas
- Technology
- Battery: 203 MW · Battery
- Total requested
- 203 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 15 December 2022
- Agreement signed
- 14 August 2024
- Proposed online date
- April 2028
Location
Marker shows the centre of Dickens County; the queue data does not give exact sites.
Other requests in Dickens County
- Donegal SolarSolar · 202 MW · agreement signed
- Wolf Spring SolarSolar + storage · 196 MW · agreement signed
- Corruscant BESSBattery storage · 402 MW · in study
- Spurland Solar ISolar · 302 MW · in study
- Outrider BESSBattery storage · 302 MW · in study
- Sanders Hollow Energy CenterOnshore wind · 293 MW · in study
- Timberlakes SolarSolar · 204 MW · in study
- Spurland Solar IISolar · 202 MW · in study
- Academy WindOnshore wind · 305 MW · suspended
- Dickens BESSOther · 201 MW · built
- Burksol BESSOther · 103 MW · built
- Aquamarine SolarSolar · 152 MW · withdrawn