ONSHORE WIND Β· ERCOTWOE Gyp King Wind
WOE Gyp King Wind is a 304 MW onshore wind request suspended in the ERCOT interconnection queue, in King County, Texas.
Queue statusPaused / redesign
- PlanningQueued Apr 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0401
- Grid region
- ERCOT (Texas)
- Developer
- KSK Wind Farm 1, LLC
- Connection point (POI)
- Tap 138kV 33798 GYP_18 βΓΓ¬ 6088 BENJ4A
- Location
- King County, Texas
- Technology
- Wind: 304 MW
- Total requested
- 304 MW
- Study phase
- FIS
- Queue status
- Suspended
- Entered queue
- 18 April 2023
- Proposed online date
- December 2029
Location
Marker shows the centre of King County; the queue data does not give exact sites.
Other requests in King County