🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Southfork Energy Storage

Southfork Energy Storage is a 306 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Kimble County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0653
Grid region
ERCOT (Texas)
Developer
Southfork Energy Storage, LLC
Connection point (POI)
tap 345kV 60709 Oersted - 60616 Edison CKT 1
Location
Kimble County, Texas
Technology
Battery: 306 MW
Total requested
306 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 July 2024
Proposed online date
November 2028

Location

Marker shows the centre of Kimble County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Kimble County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem