United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 33

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 33 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Elion Energy Storage
Battery storage
302 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Tyrell Energy Storage
Battery storage
302 MWAgreement signed Orange, CACAISO Apr 2021target 2032
Priddy Wind
Onshore wind · ENGIE North America
302 MWAgreement signed Mills, TXERCOT Jan 2015target 2026
Tabla Energy Storage
Battery storage
302 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2032
Uva Creek Solar
Solar · Grape Creek Solar, LLC
302 MWAgreement signed Borden, TXERCOT Feb 2024target 2028
Spurland Solar I
Solar · Spurland Solar I
302 MWIn study Dickens, TXERCOT Nov 2025target 2028
Outrider BESS
Battery storage · Sanders Hollow Energy Center, LLC
302 MWIn study Dickens, TXERCOT Jun 2025target 2028
Onshore wind project G0366, Morrow County
Onshore wind
302 MWIn study Morrow, ORWest May 2009target 2014
Onshore wind project GEN-2016-111, Mcpherson County
Onshore wind
302 MWAgreement signed Mcpherson, KSSPP Nov 2016target 2027
Dry Creek Solar II
Solar · Oak Hill Solar II LLC
302 MWIn study Rusk, TXERCOT Jun 2025target 2028
Silver Dollar Solar
Solar + storage · Silver Dollar Solar Project, LLC
302 MWIn study Freestone, TXERCOT Jun 2024target 2028
Badger Solar
Solar + storage · 174 Power Global Properties, LLC
302 MWIn study Upton, TXERCOT Feb 2025target 2029
Dairyland Storage
Battery storage · ENGIE IR Holdings LLC
302 MWIn study Hopkins, TXERCOT Apr 2025target 2029
HyFuels Calhoun Solar
Solar · HyFuels Green Lake Solar LLC
302 MWIn study Victoria, TXERCOT Oct 2022target 2027
BRP Passu BESS
Battery storage · BRP Passu BESS LLC
302 MWIn study Wilbarger, TXERCOT Dec 2020target 2028
Triangle Ranch Alpha
Onshore wind · Triangle Ranch Wind
302 MWIn study Cottle, TXERCOT Oct 2022target 2029
Whitewright Solar 2
Solar · SunWR, LLC
302 MWIn study Grayson, TXERCOT Dec 2023target 2028
Cazadores Solar
Solar · OCI Energy LLC
302 MWIn study Duval, TXERCOT Jul 2025target 2029
Soluce Bravo Storage
Solar + storage · BNPB1, LLC
302 MWIn study Brown, TXERCOT Jan 2025target 2028
Winters Glow Solar
Solar + storage · Winters Glow Solar, LLC
302 MWIn study Runnels, TXERCOT Oct 2024target 2028
Galaxy Solar 2
Solar · Galaxy Solar 2, LLC
302 MWIn study Ellis, TXERCOT Jun 2025target 2029
Amerada Solar
Solar + storage · Amerada Solar, LLC
302 MWIn study Freestone, TXERCOT May 2023target 2028
Simsboro Storage
Battery storage · Simsboro Storage LLC
302 MWIn study Freestone, TXERCOT Jun 2025target 2029
Sisters Solar
Solar + storage · Oberon Solar LLC
302 MWAgreement signed Ector, TXERCOT Feb 2019target 2027
Riverbend Solar SLF
Solar + storage · Riverbend Renewables, LLC
302 MWIn study Falls, TXERCOT Mar 2023target 2027
Sunburst Solar
Solar + storage · Indigo Solar, LLC
302 MWIn study San Patricio, TXERCOT Oct 2024target 2029
Tapaderos Solar
Solar + storage · Tapaderos Solar, LLC
302 MWIn study Young, TXERCOT Nov 2024target 2028
El Sauz Ranch
Onshore wind · El Sauz Ranch Wind, LLC
302 MWAgreement signed Willacy, TXERCOT Jun 2018target 2026
Crater BESS
Battery storage · BRP Crater BESS LLC
302 MWIn study Howard, TXERCOT May 2020target 2028
Ciervo Wind
Onshore wind · RWE Clean Energy Development, LLC
302 MWIn study Jim Hogg, TXERCOT Dec 2024target 2028
Pine Forest Solar
Solar · Pine Forest Solar I, LLC
302 MWAgreement signed Hopkins, TXERCOT Oct 2018target 2025
Rubicon Power BESS
Battery storage · Rubicon Power LLC
301 MWIn study Brazoria, TXERCOT Nov 2023target 2026
Quela BESS
Battery storage · BRP Quela BESS LLC
301 MWIn study Bexar, TXERCOT Sep 2020target 2027
Gulf Gateway Storage One
Solar + storage · Gulf Gateway Storage, LLC
301 MWIn study San Patricio, TXERCOT Aug 2025target 2027
Gulf Gateway Solar One
Solar + storage · Gulf Gateway Solar, LLC
301 MWIn study San Patricio, TXERCOT Apr 2025target 2027
Cenizo Solar
Solar · Renew Development Holdco, LLC
301 MWIn study Webb, TXERCOT Nov 2025target 2029
Themisto Solar
Solar · Themisto Solar, LLC
301 MWIn study Nolan, TXERCOT Feb 2024target 2028
Seine BESS
Battery storage · BRP Seine BESS LLC
301 MWAgreement signed Foard, TXERCOT Dec 2020target 2027
Cernan BESS
Battery storage · Scarlet BESS LLC
301 MWIn study Wharton, TXERCOT Feb 2025target 2027
Palomino Solar
Solar + storage · Palomino Renewables
301 MWIn study Hopkins, TXERCOT Oct 2024target 2028
Horseshoe Bend Solar
Solar · Clenera
301 MWIn study Brown, TXERCOT Jun 2017target 2027
Sweetheart Solar
Solar + storage · Sweetheart Energy, LLC
301 MWIn study Young, TXERCOT Aug 2025target 2029
Prairie Branch Solar
Solar + storage · Prairie Branch Solar
301 MWIn study Montague, TXERCOT Sep 2025target 2028
Blue Spring Solar
Solar · Flat Creek Solar, LLC
301 MWIn study Haskell, TXERCOT Oct 2025target 2028
Sundance Solar
Solar · Sundance Solar, LLC
301 MWIn study Knox, TXERCOT Apr 2025target 2029
Apricot Sun Storage
Solar + storage · Apricot Sun Energy Center, LLC
301 MWIn study Duval, TXERCOT Apr 2025target 2029
Acker BESS
Battery storage · Ogallala BESS LLC
301 MWAgreement signed Castro, TXERCOT Jun 2023target 2028
Barranca Wind 1
Onshore wind · Barranca Wind Energy, LLC
301 MWIn study Jim Hogg, TXERCOT Jul 2025target 2028
Great Rock BESS
Battery storage · Black Mountain Energy Storage II
301 MWAgreement signed Leon, TXERCOT Nov 2022target 2027
Jaguar Solar
Solar + storage · PP Jaguar Solar LLC
301 MWAgreement signed Mclennan, TXERCOT Mar 2021target 2027
Page 33 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)