United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Acker BESS

Acker BESS is a 301 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Castro County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0460
Grid region
ERCOT (Texas)
Developer
Ogallala BESS LLC
Connection point (POI)
23912 Ogallala 345 kV
Location
Castro County, Texas
Technology
Battery: 301 MW
Total requested
301 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
7 June 2023
Agreement signed
21 April 2025
Proposed online date
April 2028

Location

Marker shows the centre of Castro County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Castro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem