🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Scarlet Solar

Scarlet Solar is a 180 MW solar request in interconnection study in the ERCOT interconnection queue, in Castro County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0015
Grid region
ERCOT (Texas)
Developer
Innovative Solar 416, LLC
Connection point (POI)
tap 345kV 23912 Ogallala - 23910 Windmill
Location
Castro County, Texas
Technology
Solar: 180 MW
Total requested
180 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
11 December 2019
Proposed online date
August 2025

Location

Marker shows the centre of Castro County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Castro County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem