United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Barranca Wind 1

Barranca Wind 1 is a 301 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Jim Hogg County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0375
Grid region
ERCOT (Texas)
Developer
Barranca Wind Energy, LLC
Connection point (POI)
Tap the 345 kV CENIZO (#80225) - DELSOL (#80307) line
Location
Jim Hogg County, Texas
Technology
Wind: 301 MW
Total requested
301 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
29 July 2025
Proposed online date
June 2028

Location

Marker shows the centre of Jim Hogg County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jim Hogg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem