United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Bell Song Solar 3

Bell Song Solar 3 is a 168 MW solar request in interconnection study in the ERCOT interconnection queue, in Jim Hogg County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
31INR0009
Grid region
ERCOT (Texas)
Developer
Bell Song Solar, LLC_3
Connection point (POI)
Tap 345 kV #80079 CRUCE7A - #80355 DELSOL7A ckt 1
Location
Jim Hogg County, Texas
Technology
Solar: 168 MW
Total requested
168 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 June 2025
Proposed online date
August 2030

Location

Marker shows the centre of Jim Hogg County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Jim Hogg County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem