🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Prairie Branch Solar

Prairie Branch Solar is a 301 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Montague County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0422
Grid region
ERCOT (Texas)
Developer
Prairie Branch Solar
Connection point (POI)
Tap 345kV #1730 Krum West - #6111 Riley Ckt 1
Location
Montague County, Texas
Technology
Solar: 301 MW · Battery
Total requested
301 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
9 September 2025
Proposed online date
June 2028

Location

Marker shows the centre of Montague County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Montague County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem