SOLAR + STORAGE · ERCOTWinters Glow Solar
Winters Glow Solar is a 302 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Runnels County, Texas.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0198
- Grid region
- ERCOT (Texas)
- Developer
- Winters Glow Solar, LLC
- Connection point (POI)
- tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF
- Location
- Runnels County, Texas
- Technology
- Solar: 302 MW · Battery
- Total requested
- 302 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 29 October 2024
- Proposed online date
- September 2028
Location
Marker shows the centre of Runnels County; the queue data does not give exact sites.
Other requests in Runnels County
- Norton SolarSolar · 129 MW · agreement signed
- Rutile BESSBattery storage · 101 MW · agreement signed
- Sawtooth SolarSolar · 201 MW · in study
- Winters Glow StorageSolar + storage · 155 MW · in study
- Dexter SolarSolar · 330 MW · withdrawn
- Dexter StorageOther · 325 MW · withdrawn
- Wagon Wheel SolarSolar · 145 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem