Dexter Solar

Dexter Solar is a 330 MW solar request withdrawn in the ERCOT interconnection queue, in Runnels County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0213
Grid region
ERCOT (Texas)
Developer
241BB 8me LLC
Connection point (POI)
tap 345kV 60040 Bluff Creek - 6444 Red Creek
Location
Runnels County, Texas
Technology
Solar: 330 MW
Total requested
330 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
4 March 2019
Proposed online date
May 2023
Withdrawn
May 2021

Location

Marker shows the centre of Runnels County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Runnels County