United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTNorton Solar
Norton Solar is a 129 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Runnels County, Texas.
Queue statusConsented
- PlanningQueued Mar 2017 (completed)
- ConsentedJun 2019 (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 19INR0035
- Grid region
- ERCOT (Texas)
- Developer
- TAI Norton Solar, LLC
- Connection point (POI)
- 60451 Garnet 138kV
- Location
- Runnels County, Texas
- Technology
- Solar: 129 MW
- Total requested
- 129 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 6 March 2017
- Agreement signed
- 20 June 2019
- Proposed online date
- November 2025
Location
Marker shows the centre of Runnels County; the queue data does not give exact sites.
Other requests in Runnels County
- Rutile BESSBattery storage · 101 MW · agreement signed
- Winters Glow SolarSolar + storage · 302 MW · in study
- Sawtooth SolarSolar · 201 MW · in study
- Winters Glow StorageSolar + storage · 155 MW · in study
- Dexter SolarSolar · 330 MW · withdrawn
- Dexter StorageOther · 325 MW · withdrawn
- Wagon Wheel SolarSolar · 145 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem