Rubicon Power BESS

Rubicon Power BESS is a 301 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0096
Grid region
ERCOT (Texas)
Developer
Rubicon Power LLC
Connection point (POI)
39703 TNMP FM524 138kV
Location
Brazoria County, Texas
Technology
Battery: 301 MW
Total requested
301 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
14 November 2023
Proposed online date
December 2026

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County