🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Straight Spur Storage

Straight Spur Storage is a 306 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Andrews County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0386
Grid region
ERCOT (Texas)
Developer
ENGIE IR Holdings LLC
Connection point (POI)
Tap 345kV ClearFork( Bus # 23876) to Gardenale Switch (Bus # 11157)
Location
Andrews County, Texas
Technology
Battery: 306 MW · Battery
Total requested
306 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 November 2024
Proposed online date
April 2029

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Andrews County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem