SOLAR Β· ERCOT

Eunice Solar

Eunice Solar is a 427 MW solar request built and operating in the ERCOT interconnection queue, in Andrews County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2018 (completed)
  2. ConsentedDec 2019 (completed)
  3. Construction (completed)
  4. OperatingSep 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0219
Grid region
ERCOT (Texas)
Developer
2W Permian Solar LLC
Connection point (POI)
tap 345kV 79650 Clearfork - 79630 Telephone Rd
Location
Andrews County, Texas
Technology
Solar: 427 MW
Total requested
427 MW
Study phase
IA
Queue status
Operational
Entered queue
5 December 2018
Agreement signed
11 December 2019
Proposed online date
August 2021
Came online
September 2021

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Andrews County