Rodeo Solar

Rodeo Solar is a 200 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Andrews County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedAug 2019 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0103
Grid region
ERCOT (Texas)
Developer
Core Solar SPV I, LLC
Connection point (POI)
138kV 11273 NELSON SWITCH
Location
Andrews County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
29 June 2017
Agreement signed
20 August 2019
Proposed online date
November 2026

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.