SOLAR · ERCOTRodeo Solar
Rodeo Solar is a 200 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Andrews County, Texas.
Queue statusConsented
- PlanningQueued Jun 2017 (completed)
- ConsentedAug 2019 (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 19INR0103
- Grid region
- ERCOT (Texas)
- Developer
- Core Solar SPV I, LLC
- Connection point (POI)
- 138kV 11273 NELSON SWITCH
- Location
- Andrews County, Texas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 29 June 2017
- Agreement signed
- 20 August 2019
- Proposed online date
- November 2026
Location
Marker shows the centre of Andrews County; the queue data does not give exact sites.
Other requests in Andrews County
- Solar + storage project GEN-2024-280, Andrews CountySolar + storage · 350 MW · in study
- Straight Spur StorageSolar + storage · 306 MW · in study
- Straight Spur SolarSolar + storage · 252 MW · in study
- Straight Spur WindOnshore wind · 247 MW · in study
- Trivor BESSBattery storage · 206 MW · in study
- BRP Kabru BESSBattery storage · 203 MW · in study
- BRP Kamet BESSBattery storage · 203 MW · in study
- Tucana BESSBattery storage · 201 MW · in study
- Desert Rose SolarSolar · 200 MW · suspended
- Whatley SolarSolar · 150 MW · suspended
- Eunice SolarSolar · 427 MW · built
- Prospero Solar***Solar · 300 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem