United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTLaurel Wind Energy Center
Laurel Wind Energy Center is a 307 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.
Queue statusConsented
- PlanningQueued Jun 2023 (completed)
- ConsentedOct 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 27INR0056
- Grid region
- ERCOT (Texas)
- Developer
- LAUREL ENERGY CENTER, LLC
- Connection point (POI)
- Solstice to Bakersfield (Bus# 60404 -76002) 345kV Ckt 2 line tap
- Location
- Pecos County, Texas
- Technology
- Wind: 307 MW
- Total requested
- 307 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 28 June 2023
- Agreement signed
- 25 October 2024
- Proposed online date
- March 2027
Location
Marker shows the centre of Pecos County; the queue data does not give exact sites.
Other requests in Pecos County
- Longfellow Solar IISolar + storage · 207 MW · agreement signed
- Pecos Storage CenterWind + storage · 201 MW · agreement signed
- Longfellow Solar ISolar + storage · 178 MW · agreement signed
- Headcamp Energy Storage PlantBattery storage · 153 MW · agreement signed
- Longfellow BESS IISolar + storage · 106 MW · agreement signed
- Sherbino II BESS SLFBattery storage · 77.4 MW · agreement signed
- Longfellow BESS ISolar + storage · 55.0 MW · agreement signed
- Downtown BESSBattery storage · 10.0 MW · agreement signed
- Alamo Street BESSBattery storage · 10.0 MW · agreement signed
- Indian Mesa repowerOnshore wind · 9.3 MW · agreement signed
- Desert Sky repowerOnshore wind · 7.2 MW · agreement signed
- Sherbino II Wind repowerOnshore wind · -18.0 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem