BATTERY STORAGE · ERCOT

Sherbino II BESS SLF

Sherbino II BESS SLF is a 77.4 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2023 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0296
Grid region
ERCOT (Texas)
Developer
Phoenix Battery Storage, LLC
Connection point (POI)
38430 TNMP White baker Switching Station 138kV
Location
Pecos County, Texas
Technology
Battery: 77.4 MW
Total requested
77.4 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
30 November 2023
Agreement signed
1 August 2024
Proposed online date
February 2027

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem