Longfellow Solar II

Longfellow Solar II is a 207 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2022 (completed)
  2. ConsentedApr 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0454
Grid region
ERCOT (Texas)
Developer
CENTURY GAS PROCESSING, LLC
Connection point (POI)
38432 TNCENTRY2_1 138 KV
Location
Pecos County, Texas
Technology
Solar: 207 MW · Battery
Total requested
207 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
7 November 2022
Agreement signed
15 April 2025
Proposed online date
June 2027

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem