🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Downtown BESS

Downtown BESS is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusConsented
  1. Planning (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0764
Grid region
ERCOT (Texas)
Developer
Fort Stockton Clean Energy Center, LLC
Connection point (POI)
New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Downtown TSP Station Code: TNFS Load Name: LOAD2 Bus #: PTI Bus Number: 38360 Voltage (Transmission level kV): 69kV Node (l
Location
Pecos County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
IA Executed
Queue status
Active
Agreement signed
27 December 2024
Proposed online date
January 2026

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem