WIND + STORAGE · ERCOT

Pecos Storage Center

Pecos Storage Center is a 201 MW wind + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusConsented
  1. PlanningQueued Sep 2023 (completed)
  2. ConsentedOct 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
27INR0080
Grid region
ERCOT (Texas)
Developer
Laurel Energy Center, LLC
Connection point (POI)
Tap 345kV 60404 Solstice - 76002 Bakersfield Ckt 2
Location
Pecos County, Texas
Technology
Battery: 201 MW · Battery
Total requested
201 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
7 September 2023
Agreement signed
25 October 2024
Proposed online date
March 2027

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem