United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Headcamp Energy Storage Plant

Headcamp Energy Storage Plant is a 153 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2021 (completed)
  2. ConsentedFeb 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0401
Grid region
ERCOT (Texas)
Developer
Momentum Headcamp LLC
Connection point (POI)
tap 138kV 38331 TN Alamo St – 38455 TN Holiday
Location
Pecos County, Texas
Technology
Battery: 153 MW
Total requested
153 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
3 December 2021
Agreement signed
16 February 2024
Proposed online date
November 2025

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem