🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Indian Mesa repower

Indian Mesa repower is a 9.3 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusConsented
  1. PlanningQueued May 2018 (completed)
  2. ConsentedDec 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
18INR0069
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
76019 Indian NWP 138kV
Location
Pecos County, Texas
Technology
Wind: 9.3 MW
Total requested
9.3 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
22 May 2018
Agreement signed
4 December 2018
Proposed online date
December 2026

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem