ONSHORE WIND · ERCOT

Live Oak Wind II

Live Oak Wind II is a 303 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Schleicher County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0280
Grid region
ERCOT (Texas)
Developer
ENGIE IR Holdings LLC
Connection point (POI)
#76003 Big Hill 345kV
Location
Schleicher County, Texas
Technology
Wind: 303 MW
Total requested
303 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
24 March 2025
Proposed online date
September 2028

Location

Marker shows the centre of Schleicher County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Schleicher County