United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Copperleaf Energy Storage

Copperleaf Energy Storage is a 307 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wichita County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0118
Grid region
ERCOT (Texas)
Developer
Copperleaf Energy Storage, LLC
Connection point (POI)
Tap 345kV Fisher Road Switch (#1425) – Riley (#6101)
Location
Wichita County, Texas
Technology
Battery: 307 MW
Total requested
307 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 November 2024
Proposed online date
April 2029

Location

Marker shows the centre of Wichita County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wichita County