Adamstown Solar is a 251 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Wichita County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2018 (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0210
Grid region
ERCOT (Texas)
Developer
Adams Creek Solar Project, LLC
Connection point (POI)
tap 345kV 1730 West Krum - 6111 Riley Ckt 2
Location
Wichita County, Texas
Technology
Solar: 251 MW
Total requested
251 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
20 November 2018
Agreement signed
4 December 2024
Proposed online date
August 2027

Location

Marker shows the centre of Wichita County; the queue data does not give exact sites.