BATTERY STORAGE · ERCOT

Bologna BESS

Bologna BESS is a 203 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wichita County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0472
Grid region
ERCOT (Texas)
Developer
MALONEY BESS LLC
Connection point (POI)
Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend
Location
Wichita County, Texas
Technology
Battery: 203 MW
Total requested
203 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
29 March 2024
Proposed online date
April 2028

Location

Marker shows the centre of Wichita County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wichita County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem