United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Pethrus BESS

Pethrus BESS is a 174 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wichita County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0280
Grid region
ERCOT (Texas)
Developer
Pethrus BESS, LLC
Connection point (POI)
Tap Wichita Falls Switch (#1464) – North Star (#1467) 138 kV Line
Location
Wichita County, Texas
Technology
Battery: 174 MW
Total requested
174 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
23 September 2023
Proposed online date
February 2028

Location

Marker shows the centre of Wichita County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Wichita County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem